CHAPTER ONE
1. INTRODUCTION
It is a conventional practice to rest the
foundations of major bridges anchored firmly into sound rock. Streams where fundable
strata is not available at a reasonable depth, always pose a problem to select appropriate
type of foundations. The bridge engineers generally do not like to deviate from
guide lines given in the IRC codes1,2,3,4 which are general in nature covering
various conditions all over the country. The bridge engineer, however, has to
exercise his insight to adopt unique solution, to suit a particular site
conditions. Such decisions a build up confidence level, if they are supported
by sound performance record of precedents.
Over the years, Maharashtra state has
developed raft foundations as available alternative for deep foundations such
as wells and piles in locations where hard foundable strata are deep seated and
dry weather flow is such that construction of cut off walls with manual open
excavation is feasible. Recognizing the indisputable merits of raft foundation,
design and construction, engineers of the department have been constantly innovating
to achieve economy and furtherance of constructional ease. Construction of cut
off walls upto desired depth is possible by excavating an open trench in case
of cohesive soils which can be vertically cut. Dewatering is one of the major
difficulties faced in the construction of raft foundations6 especially in case
of sandy soils and structures near irrigated areas because recharging of the
ground makes dewatering difficult. Various innovative methods7 have been
devised and put into practice in the field to overcome such difficulties.
1.1
Statement
of the Problems
The bed material predominantly consists of
pure sand with almost no silt/clay content & could not stand a vertical cut
necessary to allow excavation of an open trench. The work was, however,
commenced with a conventional method of excavating a wide open trench. A block
of 28.0 m x 10.0 m was excavated in the sandy bed. The pit could hardly be
excavated to a depth of 1.50 m below the bed level & it was observed that
further digging is not possibly due to following impediments:
(a) Collapse of sides due to heavy sand blows
during excavation
& dewatering, inspite of shoring &
strutting.
(b) The water level remained constant even
after employing 200 HP water pumps for dewatering.
Further work was hampered due to occurrence
of non–seasonal floods & the excavated pit got filled up to the original
bed level. It was therefore considered necessary to explore the possibility of
casting the cut off walls at bed level & thereafter lowering it down to the
desired level below the bed, instead of conventional method of casting in situ
in open trench.
1.3
Objectives of the Study
The broad objectives of the Detail Project
Report (DPR) are to determine a technically and economically viable water
supply project for a phased implementation to meet the requirements of the year
2021. Following are the specific objectives:
1. Assessment of the existing supply
situation
2. Population and water demand projections
3. Planning for Projects identified for
JnNURM
4. Project scheduling & cost estimates
5. Projects phasing
6. To prepare operational plan
7. To assess environmental and social impact
1.4
Scope & Limitations of the study
1. The study is limited to Rajkot city
admeasuring area app.104.86 sq.kms.
2. The study is limited to Water supply
projects for Rajkot city which are identified and outlined in City Development
Plan ( 2005-2012)
3. Projects which are identified in CDP for
RUDA area are excluded.
1.5 Specifications
the following abbreviations are used :
IS
: Indian Standard ANSI : American National Standards Institute
API
: American Petroleum Institute
ASME
: American Society of Mechanical Engineers
ASTM
: American Society of Testing and Materials
AWS
: American Welding Society
AWWA
: American Water Works Association
ISO
: International Organisation for Standaridisation
DIN
: Deutsches Institute fur Normung
BS
: British Standard
IEC
: International Electrotechnical Commission
IEE
: Institution of Electrical Engineers
IEEE
: Institute of Electrical and Electronic Engineers
NEMA
: National Electrical Manufacturers Association
AGMA
: American Gear Manufacturer’s Association
Order the full materials for this project from chapter one to References.
Was it interesting? If it was then don’t forget
to share this Project Materials with your other friends and circle too. You may
never know that your share may be proven helpful for many of the Final Year
Student out there. So, keep sharing and liking our content over social media
and Google plus.
No comments:
Post a Comment
Add Comment